7.1 The chapter seeks to:
- Demonstrate the deliverability of the key regeneration projects included in this Area Action Plan by outlining the committed projects, the infrastructure which have been identified and the key partners involved in delivery
- Provide an account of how each policy will be effectively monitored and the contingency plans
7.2 The Vision and Strategic Objectives for the Central Area evolved through consultation, national policies and the technical evidence base. Through this plan making process, policies have been formulated to fulfil the Vision for the Central Area by 2026. Table 7.2 ‘Schedule 1: Strategic Objectives and Central Area Action Plan Policy – Conformity Matrix’ demonstrates how each policy meets the each of the eight relevant strategic objectives.
7.3 Key to the success of these policies is their delivery. To ensure that the Council’s Vision for the Central Area is met, the Council will continue to work in partnership with a range of key stakeholder’s from the public, private, community and voluntary sectors to secure regeneration and to ensure that development management policies are complied with. These partnership arrangements will include (and / or their successor bodies where relevant) the:
- West Northamptonshire Development Corporation
- Northamptonshire County Council
- Highways Agency
- West Northamptonshire Joint Planning Unit
- University of Northampton
- Business Improvement District
- Health care commissioning bodies
7.4 A monitoring system is required in order to assess the effective delivery of each policy. This chapter contains the following:
- A summary of how each of the policies conforms to the relevant Strategic Objectives and Policies (Table 7.2 ‘Schedule 1: Strategic Objectives and Central Area Action Plan Policy – Conformity Matrix’).
- A summary of the how the Council intends to monitor the effectiveness of the Central Area Action Plan policies (Table 7.4 ‘Schedule 3: Monitoring Central Area Action Plan Policies)’.
- A summary of the key projects where there are commitments from delivery partners, and; where funding mechanisms are either in place or in the process of being sought (Table 7.3 ‘Schedule 2: Delivery of Key Development Projects (May 2012)’.
7.5 The successful delivery of the Central Area Action Plan’s key regeneration initiatives is reliant upon effective, coordinated and committed delivery from all key partners; as well as the ability to secure private commercial interest and investment. Within the Central Area a cautious but realistic approach to delivery of the ‘Strategic Objectives’ and the delivery of policies major development sites Chapter 6.1 ‘Major Development Sites Policies’ has been taken. However, this should not preclude the delivery of development in advance of the timescales set out in Appendix: G ‘Development Sites Indicative Outputs in the Plan Period’, provided that it does not prejudice the proper delivery of the plan and the Vision and Strategic Objectives.
7.6 There are various delivery models, which will be used to deliver these projects. Table 7.3 ‘Schedule 2: Delivery of Key Development Projects (May 2012)’ demonstrates the extent to which these models are being used and the status of key projects. The key models affecting the delivery of the Central Area Action Plan are outlined below.
7.7 For Northampton, a key delivery vehicle is the West Northamptonshire Development Corporation. In their role as enabler and deliverer, together with local authority partners, utility companies, community organisations and other key partners, they have worked towards the preparation of 5 key priority sites in Northampton. The Central Area’s infrastructure requirements will be incorporated into the West Northamptonshire Infrastructure Delivery Plan, which will be part of the West Northamptonshire Joint Core Strategy.
7.8 Growth Area Funds channelled through the West Northamptonshire Development Corporation have already been used to deliver some key projects in the Central Area, including improvements to the public realm along Black Lion Hill and Gold Street and to enable site assembly within the Waterside area.
7.9 The West Northamptonshire Development Corporation has the powers and the funds to undertake compulsory purchase orders, for example, at the Avon / Nunn Mills development site to enable delivery of suitable access to the site. As a delivery vehicle, West Northamptonshire Development Corporation has also engaged continuously with Network Rail as part of the need to redevelop Castle Station together with a mixed-use commercial scheme.
7.10 This delivery model requires involvement or funding from one or more agency, sharing joint objectives and cooperating together to ensure that these common objectives are met. In the broadest sense, this model covers all types of collaboration across the interface between the public and private sectors. It can be used to deliver policies, services and infrastructure through development agreements or similar joint venture arrangements.
7.11 Such agreements detail the matters that are required to enable the development work to start and have been used to progress:
- The redevelopment of the Grosvenor Centre – In December 2009, a Development Agreement was signed between the Borough Council and Legal & General. This partnership will see the demolition of the Greyfriars bus station, the development of a replacement bus interchange at Fish Market and the expansion of retail and leisure provision for the Grosvenor Centre
- The regeneration of St John’s development area – Planning permission for the development of student accommodation, ancillary communal facilities, gymnasium, educational training spaces and public realm works was approved in April 2012, which demonstrates the progress towards the regeneration of the St John’s strategic site. Construction began in July 2012.
7.12 Mainstream public funds have been the largest contributor to regeneration projects in the country and they involve, amongst others, funds from:
- Homes and Communities Agency for the delivery of housing schemes and the regeneration of brownfield sites, including enabling works. This funding stream has been used in the Central Area at Ransome Road
- Northamptonshire Enterprise Partnership for the delivery of economic regeneration initiatives and marketing tools, including improvements. This funding stream has been used in the Central Area in the Market Square
- Local Transport Plan for the delivery of key transport programmes such as junction improvements. This delivery mechanism has been used to change the character of the inner ring road along Horsemarket to improve pedestrian and cycle movement within the Central Area.
7.13 The Borough Council will continue to seek funding from these and other emerging agencies including the Local Economic Partnerships.
7.14 It is essential that development contributes appropriately, either financially and/or in kind towards the infrastructure that is required to make it acceptable and that it is brought forward at the right time. This will ensure that the growth and regeneration objectives for the Central Area are achieved.
7.15 Currently, there are two mechanisms in legislation for attaining contributions from development:
- The Community Infrastructure Levy (a standard infrastructure charge that local authorities can set through an approved charging schedule for different types of development)
- Planning obligations (generally on site, or off-site non-strategic infrastructure) through Section 106 of the Planning Act
7.16 The West Northamptonshire Joint Core Strategy, will set out the strategic approach to infrastructure provision that will be sought in association with new developments across Northampton, Daventry and South Northamptonshire through the Infrastructure Delivery Plan. This will identify infrastructure, which will require funding through pooled contributions from more than one development, as well as that which will be provided through Section 106 Agreements or from the public purse, or from a combination of sources. The Central Area Action Plan has sought to identify where site-specific contributions towards identified pieces of infrastructure
will be required. The financial cost of these contributions can be offset against any general requirements set out in the West Northamptonshire Joint Core Strategy and to be funded through the Community Infrastructure Levy.
7.17 The West Northamptonshire Infrastructure Delivery Plan is currently under review. In respect of developer contributions, a Supplementary Planning Document (SPD) on Planning Obligations will be completed in
2013. This document will address the delivery of strategic infrastructure requirements by means of the Community Infrastructure Levy or Planning Obligations, as outlined above.
7.18 Within the Central Area, developer obligations will be sought as appropriate for the following:
- Public realm improvements
- Public Transport
- Highways improvements and site access
- Pedestrian and Cycleway Improvements
- New or improved educational facilities/resources
- New and improved health facilities/resources
- Community safety initiatives
- New or improved infrastructure provision, for example, water, sewerage, electricity and flood mitigation
- New or improved recreational facilities
- Wildlife/ Habitat protection and enhancement
- Green infrastructure
- Affordable housing
7.19 The development site policies in Chapter 6 of this Plan set out relevant site specific contributions to infrastructure. New developments should meet their own infrastructure needs, whether for transport, utilities or other infrastructure. Residential schemes will be expected to make provision for affordable housing in accordance with the approved policy. Where development viability will be affected by the cost of planning obligations to such an extent that it is unlikely that the development will proceed, developers will be asked to submit a financial appraisal to support their case.
The Borough Council will require, by securing the direct provision of infrastructure and / or developer contributions, that all new developments provide the appropriate on and off-site infrastructure to mitigate the impact of development on the existing community and to provide the facilities needed, to support the new development.
The required provision of infrastructure and / or developer contributions will be sought by a requirement, as
appropriate, for a Planning Agreement with the developer in accordance with paragraphs 203 – 206 of the
National Planning Policy Framework and / or developer contributions to strategic infrastructure being sought
in accordance with the policies and approach required within the West Northamptonshire Joint Core Strategy.
The Borough Council will require developers to demonstrate that full consideration has been given to infrastructure requirements, in conjunction with the appropriate service providers and to establish that, within the timescales required:
- Adequate capacity exists to provide for the development
- New provision will be proposed either directly and / or by financial contribution and / or by proposals for the more efficient use of existing services or the promotion of behavioural change, sufficient to be equivalent to new service provision.
In the event that the developer considers that the required level of infrastructure provision is unduly onerous and will prejudice the delivery of the development proposals, the Borough Council will require the developer to undertake a Viability Assessment as part of the further consideration of an agreement linked to the determination of the development application.
The provision of infrastructure will be linked to the phasing of development in the Infrastructure Delivery Plan for West Northamptonshire, which programmes the coordinated delivery of supporting funding and the assembly of developer contributions. The infrastructure provision will be coordinated and delivered in partnership with local
authorities and agencies in West Northamptonshire and appropriate service providers, to ensure that the development proposals are delivered in a coordinated manner ensuring that proposals form part of the sustainable
growth of Northampton Central Area and Borough.
7.20 This section demonstrates the capacity and capability of delivery of proposed development and the amount and the time frame for doing so. This is summarised in Table 7.1 ‘Summary of Indicative Outputs by Phases 2011-2026’). Potential outputs from the Action Plan are detailed in Development Sites: Indicative Outputs in the Plan Period where the land use components and indicative phasing for the major development sites are listed.
7.21 Delivery of the infrastructure will be dependent upon maximising the contribution from the development process. However, a significant contribution from the public purse will also be necessary. Central Government has a key role in providing the necessary investment to achieve sustainable growth within West Northamptonshire. As well as capital investment it will need to provide appropriate revenue support to those agencies required to manage or serve such development.
7.22 It is important that the infrastructure required by local communities is delivered when the need arises. Whilst better management of projects has a key role to play, the timing of infrastructure delivery will need to take account of all the funding streams available to local communities. The process of infrastructure provision involves
a wide range of organisations providing services. Full and effective partnership working will be essential for successful delivery through agreed investment and delivery plans.
7.23 Development outputs for the major development sites will be set out in detailed Masterplans and in the development site policies (Chapter 6.1 ‘Major Development Sites Policies’) contained within the Action Plan. Appendix: H ‘Potential Housing Sites (West Northamptonshire Strategic Housing Land Availability Assessment) Outside Major Development Sites’ lists sites considered to be suitable for housing from the Strategic Housing Land Availability Assessment. There is considerable potential for these smaller sites to contribute to housing growth
within the Central Area. This contribution could be made in the early phases of the Action Plan (Phase 1: 2011-2016) at a time when, due to lead in times, the larger sites are likely to have a relatively limited output.
7.24 On the basis of available information, indicative outputs by site are identified and detailed in Appendix G. ‘Development Sites: Indicative Outputs in the Plan Period’. A summary of these outputs is given in Table 7.1 ‘Summary of Indicative Outputs by Phases 2011-2026’. The distribution of major development sites and phased completions is shown in Table 7.3 ‘Schedule 2: Delivery of Key Development Projects.
Table 7.1 Summary of Indicative Outputs by Phases 2011-2026 |
||||
Totals | ||||
Use | All Sites |
Phase 1 2011-2016 |
Phase 2 2016-2021 |
Phase 3 2021-2026 |
Retail - (square metres) |
71,050-74,050 | 4,000 | 66,050-69,050 | 1,000 |
Hotels - (beds) | 405 - 480 | 105 | 50-75 | 250+ |
Offices - (square metres) |
132,500 | 28,500 | 96,000 | 8,000 |
Housing - (Dwellings) |
3,437 | 529 | 1,523 | 1,385 |
7.25 The CAAP contains 36 policies, in addition to the key overarching policy associated with “presumption in favour of sustainable development” which each proposal will be determined against. On adoption these replace some of the saved policies and proposals contained in the Northampton Local Plan 1997. The relevant saved policies replaced are identified in Appendix: I. ‘List of Northampton Local Plan (1997) Policies that are replaced by the Policies within the Central Area Action Plan’.
7.26 Each of the policies will need to be monitored. Some of the policies can be monitored through interrogation of planning approvals, refusals and appeals. Others will be monitored through the targets and
timescale set down for each projects or the completions. The effectiveness of each of these policies will be determined generally through the:
- Strength in which these policies have been successfully used to refuse unacceptable developments and defend the decision at appeals.
- Successful delivery of each phase of the projects within the stated timescales.
- Completion and implementation of the relevant planning agreements/ Section 106 Agreements.
Table 7.2 Schedule 1: Strategic Objectives and Central Area Action Plan Policy Conformity Matrix | ||||||||
Strategic Objectives | ||||||||
Policy | SO1 | SO2 | SO3 | SO4 | SO5 | SO6 | SO7 | SO8 |
Promoting design excellence (Policy 1) | X | X | X | X | ||||
Tall Buildings (Policy 2) | X | X | ||||||
Public Realm (Policy 3) | X | X | X | |||||
Green Infrastructure (Policy 4) | X | X | X | |||||
Flood Risk and Drainage (Policy 5) | X | |||||||
Inner Ring Road (Policy 6) | X | X | X | X | ||||
Bus Interchange: Fishmarket (Policy 7) | X | X | ||||||
Safeguarded Public Transport Route (Policy 8) | X | X | ||||||
Pedestrian and Cycle Framework (Policy 9) | X | X | ||||||
Parking (Policy 10) | X | |||||||
Town Centre boundary (Policy 11) | X | X | X | |||||
Definition of Primary Shopping Area (Policy 12) | X | X | ||||||
Improving the Retail Offer (Policy 13) | X | X | ||||||
Meeting Retail Capacity (Policy 14) | X | X | ||||||
Office and Business Use (Policy 15) | X | X | X | |||||
Central Area Living (Policy 16) | X | X | X | |||||
Grosvenor Centre (Policy 17) | X | X | X | X | X | X | X | |
Abington Street East (Policy 18) | X | X | ||||||
Castle Station (Policy 19) | X | X | ||||||
St. John's (Policy 20) | X | X | X | X | X | X | X | |
Angel Street (Policy 21) | X | X | X | X | X | X | X | |
Bridge Street (Policy 22) | X | X | X | X | X | X | X | |
Upper Mounts/Great Russell Street (Policy 23) | X | X | X | X | ||||
Spring Boroughs (Policy 24) | X | X | X | X | X | |||
The Waterside (Policy 25) | X | X | ||||||
The Waterside: Brampton Branch St. Peter's Way (Policy 26) | X | X | X | X | X | X | X | |
The Waterside: Southbridge West (Policy 27) | X | X | X | X | X | X | X | |
The Waterside: Avon/Nunn Mills/Ransome Road (Policy 28) | X | X | X | X | X | X | X | |
The Waterside: Becket's Park (Policy 29) | X | X | X | X | X | X | X | |
The Waterside: Nene Meadows (Policy 30) | X | X | X | |||||
Market Square (Policy (31) | X | X | X | X | X | |||
Drapery (Policy 32) | X | X | X | X | ||||
Freeschool Street (Policy 33) | X | X | X | X | ||||
Former Royal Mail Sorting Office (Policy 34) | X | X | X | |||||
Telephone Exchange, Spring Boroughs (Policy 35) | X | X | X | X | ||||
Infrastructure Delivery (Policy 36) | X | X | X | X | X | X | X | X |
References within the table:
NBC: Northampton Borough Council
NCC: Northamptonshire County Council
WNDC: West Northamptonshire Development Corporation
EA: Environment Agency
HCA: Homes and Communities Agency
RNRP: River Nene Regional Park
Table 7.3 Schedule 2: Delivery of Key Development Projects (May 2012) | ||||||||
Where |
When (Timescale for delivery) |
Why |
Specific development requirements |
Lead delivery organisation |
Estimated Cost |
Sources of funding |
Any dependencies |
Project Status |
Fishmarket (Policy 7) |
CAAP Phase 1 |
To replace Greyfriars Bus Station |
Bus interchange providing sufficient capacity for bus demand up to 2026 | NBC; NCC; WNDC; Bus operators | £5m | NBC; WNDC; NCC | Planning application approved in July 2012 | |
Grosvenor Centre (Policy 17) | Anticipated demolition of the Greyfriars bus station and start of works for extension 2013; opening of Grosvenor Centre (Phase 1) 2017; completion of Grosvenor Centre (Phase 2) 2018 (CAAP Phases 1 and 2) | To improve and increase retail capacity and upgrade facilities; improve connectivity within the Town Centre | Retail (37,000 m2) | NBC; Legal and General; WNDC; NCC | £220m | Public and private sector funding | Bus station relocation to enable demolition of Greyfriars bus station | Development Agreement between L&G and NBC signed 2009; pre-application discussions commenced 2012 |
Abington Street East (Policy 18) | CAAP Phase 2 | To increase retail offer | Retail (9,000 m2); opportunity for continued provision of library and clinic services | NBC; NCC; PCT; NHS Foundation Trust | £6m | NBC; NCC; Private Sector | Potential to relocate library | |
Castle Station (Policy 19) | Completion of GRIP 5 (Detailed design), 2013. Completion of GRIP 6 (Construction), 2015 (CAAP Phase 2) | To modernise station facility; increase operational capacity; maximise parking facilities; increase commercial offer and residential accommodation; to assist in regeneration of Spring Boroughs; improve connectivity with the wider Central Area | New passenger railway station; Ancillary retail; residential (2700 units); office (26,000 m2); new cap parking | NBC; NCC; WNDC; NEP; Network Rail; London Midland; Dept of Transport | £44m | NBC; WNDC; Network Rail; Private Sector Developers; Government funding | Securement of public funding; Completion of the station redevelopment to release land for delivery of commercial and residential elements | GRIP 4 (single option development) now complete. 'Prior Approval' (under permitted development powers) granted 2011; Government funding secured to deliver station building |
St. John's (Policy 20) | CAAP Phase 1 | To strengthen cultural offer; increase commercial and leisure offer and residential accommodation; improve connectivity with the wider Central Area | Office (10,000 m2); hotel (105 bed); retail (A3) 200 m2); student accommodation (c.464 units) | NBC; NCC; Private Sector Developers; NEP/SEMLEP | £18m | NBC; NCC; Private Sector Developers; NEP/SEMLEP | Access from Victoria Promenade | planning application for student accommodation approved 2012; St John's surface car park closure 2012 |
Angel Street (Policy 21) | Start CAAP Phase2; complete CAAP Phase 3 | To strengthen cultural offer; increase commercial and leisure offer and residential accommodation; improve connectivity with the wider Central Area | Office (27,000 m2); hotel; residential (62 units); public civic space, mixed use development; small scale retail,financial services cafes, restaurants and bars | NBC; NCC; Private Sector Developers | £30m | NBC; NCC; Private Sector Developers | In the short term: NCC decision to relocate operation to town centre location; medium to long term: commercial potential to redevelop site | Full planning application expected 2012; business case being finalised to access viability of NCC relocating to town centre |
Bridge Street (Policy 22) | CAAP Phase 3 | To strengthen cultural offer; increase commercial and leisure offer and residential accommodation; improve connectivity with the wider Central Area | Office (8,000 m2); residential (34 units); small scale retail; financial services | NBC; NCC; Private Sector Developers | £11m | NBC; NCC; Private Sector Developers | Given current limitations to public finances it is unlikely the proposed regeneration can take place until after 2021 | |
Upper Mounts/Great Russell Street (Policy 23) | CAAP Phase 3 | Achieve comprehensive redevelopment between The Mounts and Clare Street; increase commercial and leisure offer and residential accommodation; improve connectivity with the wider Central Area | Mixed use scheme to include some / all of the following: residential; office; leisure, community and educational facilities; small scale retailing | NBC; Private Sector Developers | £4m | NBC; Private Sector Developers | Land assembly | Land owners willing to develop but waiting for market conditions to improve to initiate development |
Spring Boroughs (Policy 24) | CAAP Phase 3 | To meet Government requirements for Decent homes Standards; improve the environmental and living conditions for residents, improve connectivity to the wider Central Area; increase employment opportunities | To be determined through the Neighbourhood Planning process | NBC; Local Community; Housing Associations / Registered Social Landlords | Unknown | NBC; Housing Associations / Registered Social Landlords; Private Sector | Community engagement for future planning | 2011 sucessful bid to fund development of Neighbourhood Plan. 2012 Decent Homes Programme and the Community Energy Saving Partnership programme initiated |
The Waterside: St Peter's Way (Policy 26) | Start CAAP Phase 1; Complete CAAP Phase 3 | For effective integration between the Waterside and Central Area; to increase commercial and leisure offer and residential accommodation | office (43,000 m2); residential (270 units); public civic space | NBC; NCC; WNDC; National Grid; Carlesberg; University of Northampton | £73m plus costs associated with de-commissioning gas holders | WNDC; University of Northampton; Private Sector Developers; Government funding | The successful removal and decontamination of the gas holders; Flood risk mitigation; junction and highway related improvements to enable access and to cope with capacity issues | Formal decision on decommissioning of Gas Holders expected 2012. WNDC now owns most freehold properties. Compulsory Purchase underway on remaining freeholds / land between Castle Station and gasholder. |
The Waterside: Southbridge West (Policy 27) | CAAP Phase 3 | Development fitting for a Gateway location; improve pedestrian access along the rivers edge | Hotel (100 bed); leisure, residential or office useage (2,000 m2) | NBC; Private Sector | £8.5m | Private sector | Floor risk mitigation | |
The Waterside: Avon / Nunn Mills / Ransome Road (Policy 28) | Start CAAP Phase 1; Complete CAAP Phase 3 | For effective integration between the Waterside and Central Area; to increase residential accommodation, retail, leisure and commercial offer; education use connected with University of Northampton would also be acceptable in principle. | Office (16,000 m2); retail (2,000 m2); hotel (50-75 bed); residential (2,000 units); school; new public open space | NBC; NCC; WNDC; Network Rail; HCA; University of Northampton | £180m | WNDC, HCA and Private Sector Developers; University of Northampton | Compulsory Purchase Order of transfer of rail access (Nunn Mills); Future of disused railway line; Impact on A45 junction improvements; Flood risk mitigation; Land decontamination; New access corridor from Bedford Road to London Road | NBC and HCA agreement to provide land to enable link from Bedford Road to Ransome Road; WNDC initiated Compulsory Purchase of land at Avon / Nunn Mills; HCA procurring development partner to deliver Ransome Road - confirmation anticipated 2012-05-16 London Road / Ransome Road junction completed |
The Waterside: Becket's Park (Policy 29) | CAAP Phase 1 | To capitalise on the benefits of the river and river frontage; to improve the quality of the park and reconnect with the wider Central Area; provision of a leisure facility to increase activity and create safer environment | Leisure / recreational facility (500 m2); enabling development (residential or office) | NBC | £8.5m | Private sector | Flood risk mitigation | |
The Waterside: Nene Meadows (Policy 30) | Start CAAP Phase 1; Complete CAAP Phase 2 | To capitalise on the benefits of the river and river frontage and reconnect the site with the wider Central Area; create a strategic leisure and recreational facility that benefits people and wildlife | Leisure / recreational facility (250 m2); footpath / cycleway network; new river crossings; Local Nature Reserve enhancements; removal of earth bund; small scale interventions to increase leisure and recreational opportunities | NBC: Sustrans, EA, and Northamptonshire Wildlife Trust | £6.7m | NBC; Sustrans, EA, and Northamptonshire Wildlife Trust; private sector | Securing funding streams | Skatepark completed in 2012; Supplementary Planning Document being developed 2012 |
The Drapery (Policy 32) | CAAP Phase 2 | To increase retail capacity; extend the Primary Shopping Area; improve connectivity within the Town Centre | Retail (17,000 m2); link between Drapery and Collage Street | NBC; private secor | £20m | Private sector | Delivery of Grosvenor Centre redevelopment | |
Freeschool Street (Policy 33) | To increase retail capacity; extend the Primary Shopping Area; improve connectivity to Waterside and Town Centre | Office (2,500 m2); residential (50 units); small scale retail (c. 250 sq m) incorporating ground floor restaurant / cafe facilities; landmark building on corner of St Peter's Way and Horseshoe Street | NBC; SEMLEP / NEP; Private sector | £5.5m | NBC; SEMLEP / NEP; Private sector | The sucessful removal and decontamination of the gas holders; Land assembly; Protection and enhancement of Scheduled Monument | ||
Royal Mail Barrack Road (Policy 34) | CAAP Phase 1 | To increase offer and / or residential accommodation; improve connectivity with the wider Central Area | Redevelop / convert site for business / residential use | NBC; Private Sector Developers | £4m | Private Sector Developers | Viability for the reuse or demolition of the building | |
Telephone Exchange (Policy 35) | CAAP Phase 3 | Area enhancements by the removal of the telephone exchange which has a negative impact on the surrounding conservation area | Dwellings (50 units) | NBC; Private Sector Developers | £7m | Private Sector Developers | Decommissioning of telephone exchange |
References within the table:
EA: Environment Agency
EH: English Heritage
GRIP: Governance for Railway Investment Projects
HCA: Homes and Communities Agency
NBC: Northampton Borough Council
NCC: Northamptonshire County Council
NEP: Northampton Enterprise Partnership
SEMLEP: South East Midlands Local Enterprise Partnership
WNDC: West Northamptonshire Development Corporation
CAAP Phasing Schedule:
Phase 1: 2011 to 2016
Phase 2: 2016 to 2021
Phase 3: 2021 to 2026
7.27 The Government requires local authorities to undertake an effective monitoring of its policies through the Annual Monitoring Report, which provides details on how policies in the Local Development Documents are being achieved. In order to comply with legal requirements the policies in the Action Plan must be capable of being assessed and monitored. The criteria for this assessment and monitoring are set out in Table 7.4 ‘Monitoring Framework’ below.
Table 7.4 Monitoring Framework | |||||||
Strategic Objective 1 - Regeneration | |||||||
Objective: Expanding retail, town centre facilities and the scale of employment opportunities in the centre to match Northampton's future role as a Principal Urban Area at the heart of its sub-region, maximising the use of previously developed land | |||||||
Policy Numbers: | Policy 3, 7, 9, 11, 12, 13, 14, 15, 17, 18, 19, 20, 21, 22,23, 24, 25, 26, 27, 28, 29, 30, 31, 32, 33 | ||||||
Indicator | Target | Main Policy Delivered | Additional policies delivered | SA Objective delivered | Main Agencies for delivery / Source for monitoring data | Trigger | Contingencies |
Amount of gross retail convenience floorspace in town centre | 4,500 m2 gross convenience (food) shopping floorspace for period 2026 | Policy 11,12,13, 14 | Not site specific | SA10 | NBC, WNDC, Developers / NBC, WNJPU |
>4,500 m2 gross convenience floorspce permitted 2026 <1,500m2 gross convenience floorspace permitted by 2021 |
Review evidence base
Consider review of policy |
Amount of new gross retail comparison floorspace created in Northampton Town Centre | 61,000 m2 gross comparison shopping floorspace for period 2026 | Policy 11,12,13, 14 | Policy 17, 18, 32 | SA10 | NBC, WNDC, Developers / NBC, WNJPU |
Grosvenor Centre extension not commenced by 2016 <37,000 m2 gross comparison shopping floorspace delivered by 2021 >61,000 m2 gross comparison shopping approved floorspace for period 2026 |
Review evidence base Consider barriers to implementation Consider review of policy If the Grosvenor redevelopment does not go ahead, there will be an opportunity to capitalise on the Greyfriars site through another development. |
Annual analysis of approvals for change of use and new developments for employment use, broken down into B1, B2, B8 use classes order |
Planning permissions for developments for up to 98,500 gross sqaure metres of office space by 2016 Developments for up to 132,500 gross square metres of office space by 2021 No loss of safeguarded sites to non town centre uses |
Policy 11, 15 | Policy 19, 20, 21, 22, 26, 28,33 | SA10 | WNDC, Private Sector, NBC, Northamptonshire Enterprise Partnership, Enterprise Zone / NBC, WNJPU |
<5,000 M2 gross completions by 2016 <50,000 m2 gross completions by 2021 |
Identify reasons changes and if jobs are being created faster or slower than expected Consider allocation of additional employment land Work with developers / land owners to develop viable and suitable schemes Review policy |
Annual analysis of approvals for leisure / community uses |
Delivery of leisure facilities such as ancillary retailing, cafes, restaurants, bars, visitor centre, cycle hire (Policy 17, 19, 20, 21, 22, 23, 26, 27, 28, 29, 30, 31, and 33) Delivery of greater access to use the river and canal for a wide range of recreational activities (Policy 25, 26, 27, 28, 29, 30) |
Policy 11, 25 | Policy 17, 19, 20, 21, 22, 23, 26, 27, 28, 29, 30, 31 and 33 | SA14 | NBC, NCC, Northamptonshire Wildlife Trust, EA, Private Sector / NBC, WNJPU |
Each development listed in 'additional policies delivered' as well as each phase not commenced by the year set out in Table 7.3 and Table G.1 Each phase of Policy 26 Brampton Brancgh St Peter's Way development is not commenced by the year set out in Table G.1 Policy 27 Southbridge West is not commenced by 2021 Phase 2 of Policy 28 Avon Nunn Mills / Ransome Road is not commenced by 2021 (Table G.1) Leisure facilities in Policy 29 Becket's Park are not completed by 2021 Policy 30 Nene Meadows |
Policy reviews as part of the revision to the Central Area Action Plan to assess the future potential of the Waterside site. A revised Waterside Masterplan may need to be commissioned to inform the Central Area Action Plan review process. |
Annual analysis of % of A3 within defined frontage |
The Market Square will become the central attraction for retail and leisure uses in the Borough 40% net increase in A3 frontage in Market Square West and Market Square South to repalce existing non A1 uses. |
Policy 31 | Policy 3, 13 | SA14 | NBC, Private Sector, Town Centre BID, Town Centre Operations / NBC, WNJPU |
<12% increase in A3 frontage in Market Square West by 2021 <18% increase in A3 frontage in Market Square South by 2021 |
The thresholds for non A1 use in primary and secondary frontages around Market Square may need to be increased following further consultation and health checks. |
Annual analysis of footfall for Town Centre | 18.5% net increase in footfall in Town Centre | Policy 11, 12, 13, 14, 15, | Policy 3, 7, 9, 17, 18, 19, 20, 21, 22, 24, 26, 27, 28, 29, 30, 31, 32 | SA14 | NBC, Private Sector, Town Centre BID, Town Centre Operations / NBC, WNJPU, Town Centre Operations, Town Centre Health Check | <15% footfall in Market Square by 2021 | Policy review |
Strategic Objective 2 - A well designed Town Centre |
|||||||
Objective: Ensuring development of the highest standard that re fl ects the rich architectural heritage assets, while contributing to the rich architectural heritage and adding to the sense of place |
|||||||
Policy Numbers: |
Policy 1, 2, 3, 4, 17,18, 19, 20, 21, 22, 23, 24, 26, 27, 28, 29, 30, 31, 32, 33, 34, 35, 36 |
||||||
Indicator |
Target |
Main Policy Delivered |
Additional Policies Delivered |
SA Objective Delivered? |
Main Agencies for delivery /Source for monitoring data |
Trigger |
Contingencies |
Annual town centre health check identifying people’s perception of safety, general impression of the town centre. |
Improved perception of town centre from users related to safety |
Policy 1, 2, 3, 4, 25 |
Policy 17,18, 19, 20, 21, 22, 23, 24, 26, 27, 28, 29, 30, 31, 32, 33, 34, 35, 36 |
SA7, SA11, SA12 |
NBC, WNDC, NCC, Private Sector, Town Centre BID, Town Centre Operations / NBC, WNJPU, Town Centre Health Check |
No improved perception of town centre from users related to safety by 2016 |
Policy review as part of the revision to the Central Area Action Plan Review processes for determining applications, e.g. additional supporting document such as design guides |
Annual analysis of heritage assets |
No net increase in number of heritage assets at risk |
Policy1, 2, 3, 6, 9 |
Site- specifi c policies |
SA14 |
NBC, Developers, WNDC, English Heritage |
Increase in number of heritage assets at risk Permissions granted where there was an unresolved objection from English Heritage, NBC and NCC conservation teams |
Identify cause and consider justifi cation. |
Strategic Objective 3 - A destination of choice |
|||||||
Objective: Revitalising the Market Square at the heart of the Town Centre and create and develop cultural initiatives based around St John’s and the Derngate Theatre area |
|||||||
Policy Numbers: |
Policy 1, 3, 7, 11, 12, 13, 17, 20, 21, 22, 31, 32, 36 |
||||||
Indicator |
Target |
Main Policy Delivered |
Additional Policies Delivered |
SA Objective Delivered? |
Main Agencies for delivery /Source for monitoring data |
Trigger |
Contingencies |
Annual analysis of footfall for retail and events of the Market Square |
The Market Square will become the central attraction for retail and leisure uses in the Borough
18.5% net increase in footfall in Market Square |
Policy 3, 31 |
Policy 7, 11, 12, 13, 17, 32 |
SA14 |
NBC, private sector, Town Centre BID, Town Centre Operations / NBC, WNJPU, Town Centre Operation |
<15 % footfall in Market Square by 2021 |
The thresholds for primary and secondary frontages around Market Square may need to be increased following further consultation and health checks |
Completion of key projects related Market Square and St John’s area |
Completion of Policy 3 Public Realm Improvement, Policy 7 Bus Interchange, Policy 17 Grosvenor Centre, Policy 20 St John’s, Policy 21 Angel Street, Policy 22 Bridge Street and Policy 32 Drapery |
Policy 3, 7, 17, 20, 21, 22, 32 |
Policy 1, 36 |
SA10, SA14 |
NBC, NCC, WNDC, Private Sector, University of Northampton / NBC, WNJPU |
Each development listed in ‘Main Policies Delivered’ not commenced by the year set out in Table G. 1 (Appendix G) |
Policy review as part of the revision to the Central Area Action Plan |
Annual analysis of stall occupancy in Market Square |
Stable occupancy of permanent /casual traders by 2016
5% increase in permanent/casual traders occupancy by 202 |
Policy 31 |
|
SA14 |
NBC, Private Sector, Town Centre BID, Town Centre Operations / NBC, WNJPU, Town Centre Operations |
5% decrease in permanent/casual traders occupancy by 2016 |
Policy review as part of the revision to the Central Area Action Plan |
Increase in fl oorspace for cultural initiatives such as cinema, theatre, museum and art gallery |
600 sqm gross increase of fl oorspace for use by cultural initiatives by 2021 |
Policy 11 |
Policy 20, 21, 22 |
SA14, 15 |
NBC, Private Sector, Derngate Theatre / NBC, WNJPU |
No increase of fl oorspace for use by cultural initiatives by 2021 |
Policy review as part of the revision to the Central Area Action Plan |
Strategic Objective 4 - A walkable centre |
|||||||
Objective: Making the Central Area pedestrian friendly and ‘walkable’, with an improved public realm and linkages between key destinations |
|||||||
Policy Numbers: |
Policy 1, 3, 4, 6, 7, 8, 9, 10, 17, 20, 21, 23, 25, 26, 27, 28, 29, 30, 31, 32, 33, 34, 36 |
||||||
Indicator |
Target |
Main Policy Delivered |
Additional Policies Delivered |
SA Objective Delivered? |
Main Agencies for delivery /Source for monitoring data |
Trigger |
Contingencies |
Increase in |
1km of ‘strategic link’ Completion of removal of
|
Policy 1,3, 6, 9, 25
|
Policy 4,
|
SA1 |
NBC,WNDC,NCC, Private Sector/NBC, WNJPU |
<1km of strategic Inner Ring Road SPD No removal of subways <1km of footpaths for |
Policy review |
Amount |
1km of footpath improved |
Policy 1,3, 6, 8, 9, 25 |
Policy 4,7, 10,17, 23, |
SA1 |
NBC,WNDC,NCC, Private Sector/NBC, |
<500m increase by 2021 |
Policy review |
Strategic Objective 5 - Public transport and cycling |
|||||||
Objective: Ensuring good public transport and cycle accessibility | |||||||
Policy Numbers: |
Policy 1, 3, 4, 6, 9, 10, 17, 20, 21, 25, 26, 27, 28, 29, 30, 31, 32, 33, 34, 36 |
||||||
Indicator |
Target |
Main Policy Delivered |
Additional Policies Delivered |
SA Objective Delivered? |
Main Agencies for delivery /Source for monitoring data |
Trigger |
Contingencies |
Increase in the |
1km of strategic cycle routes improved (St Johns 1km of cycle routes for Ring Road reconfi guration |
Policy 1, 3, |
Policy 4, |
SA1 |
NBC,WNDC,NCC, Private Sector/NBC, |
<<1km of strategic Inner Ring Road SPD <1km of footpaths for |
Policy review
|
Amount of |
1km of strategic cycle 1km of cycle routes for Ring Road reconfi guration |
Policy 1, 3,
|
Policy 4,
|
SA1 |
NBC, WNDC,
|
<1km of strategic routes Inner Ring Road SPD <1km of footpaths for |
|
Strategic Objective 5 - Public transport and cycling |
|||||||
Objective: Ensuring good public transport and cycle accessibility |
|||||||
Policy Numbers: |
Policy 1, 3, 4, 6, 9, 10, 17, 20, 21, 25, 26, 27, 28, 29, 30, 31, 32, 33, 34, 36 |
||||||
Indicator |
Target |
Main Policy Delivered |
Additional Policies Delivered |
SA Objective Delivered? |
Main Agencies for delivery /Source for monitoring data |
Trigger |
Contingencies |
Delivery of a new bus interchange |
Completion of Bus Interchange by 2016 |
Policy 7 |
N/A |
SA1 |
NBC,WNDC, NCC, Private Sector /NBC, WNJPU |
Bus Interchange Not completed By 2016 |
Policy review as part of the revision to the Central Area Action Plan |
Any decommissioned railway between Brackmills and Castle Station is transformed into public transport / cycle / pedestrian route |
Some decommissioning of railway between Brackmills and Castle Station by 2026 |
Policy 8 |
N/A |
SA1 |
NBC, WNDC, NCC, Private Sector /NBC, WNJPU |
No decommissioning by 2021 |
Policy review as part of the revision to the Central Area Action Plan |
Annual analysis of number of bus users |
18.5% increase in number of bus users by 2026 |
Policy 7, 14, 15 |
Policy 10 |
SA1 |
NBC, WNDC, NCC, Private Sector /NBC, NCC, WNJPU |
<15 % increase in number of bus users by 2026 |
Policy review as part of the revision to the Central Area Action Plan |
Strategic Objective 6 - A Safer Environment |
|||||||
Objective: Providing an appealing and safe environment within the urban framework and along the Waterside |
|||||||
Policy Numbers: |
Policy 1, 3, 4, 6, 7, 9, 17, 18, 19, 20, 21, 22, 23, 24, 25, 26, 27, 28, 29, 30, 31, 32, 33, 34, 35 |
||||||
Indicator |
Target |
Main Policy Delivered |
Additional Policies Delivered |
SA Objective Delivered? |
Main Agencies for delivery /Source for monitoring data |
Trigger |
Contingencies |
Areas of town |
Completion of public |
Policy 1 and
|
Policy 4,
|
SA7 |
NBC, WNDC, NCC,
|
Public realm |
Policy review
|
Crime measures in town centre |
Decrease of crime in physical assaults, fear of crime, robbery. |
Policy 1, 3 and 25 |
Policy6 ,7, 9, 17, 18,19, 20, 21,22, 23, 24,26, 27, 28,29, 30, 31,32, 33, 34,35 |
SA7 |
NBC, WNDC, |
Increase in crime |
Identify barriers to good crime prevention by design Review processes for determining applications to deliver good design, e.g. additional supporting document such as design guides Consider policy review |
Strategic Objective 7 - Repopulate the Central Area |
|||||||
Objective: Substantially increasing the resident population through the redevelopment of redundant industrial areas and the regeneration of Spring Boroughs |
|||||||
Policy Numbers: |
Policy 16, 19, 22, 23, 24, 26, 28 |
||||||
Indicator |
Target |
Main Policy Delivered |
Additional Policies Delivered |
SA Objective Delivered? |
Main Agencies for delivery /Source for monitoring data |
Trigger |
Contingencies |
Annual analysis of approvals for change of use and new developments for housing and student accommodation |
Completion of 3,900 dwellings by 2026 |
Policy 16 |
Policy 19,22, 23, 24, 26, 28 |
SA14 |
NBC, WNDC, Private Sector, University of Northampton / NBC, WNJPU |
Each development listed in ‘Additional Policies delivered’ not commenced by the year set out in Table G.1 (Appendix G). |
Work with developer / land owner to produce a viable and suitable scheme |
Strategic Objective 8 - Sustainability |
|||||||
Objective: Ensuring the Central Area develops in a sustainable manner and helps create a positive framework for action on climate change |
|||||||
Policy Numbers: |
Policy 1, 2, 4, 5, 7, 9, 10, 14, 15, 16, 17, 18, 19, 20, 21, 22, 23, 24, 25, 26, 27, 28, 29, 30, 31, 32, 33, 34, 35, 36 |
||||||
Indicator |
Target |
Main Policy Delivered |
Additional Policies Delivered |
SA Objective Delivered? |
Main Agencies for delivery /Source for monitoring data |
Trigger |
Contingencies |
Minimum Code |
Planning Permissions: |
Policy 16 |
Policy1,2,19,22, 23,24, 26, 28 |
SA8 |
NBC, WNDC,
|
Either: |
Further Consider a |
Strategic Objective 8 - Sustainability |
|||||||
Objective: Ensuring the Central Area develops in a sustainable manner and helps create a positive framework for action on climate change |
|||||||
Policy Numbers: |
Policy 1, 2, 4, 5, 7, 9, 10, 14, 15, 16, 17, 18, 19, 20, 21, 22, 23, 24, 25, 26, 27, 28, 29, 30, 31, 32, 33, 34, 35, 36 |
||||||
Indicator |
Target |
Main Policy Delivered |
Additional Policies Delivered |
SA Objective Delivered? |
Main Agencies for delivery /Source for monitoring data |
Trigger |
Contingencies |
BREEAM Standards for Non-Residential Development |
Planning Permissions for Non-Residential Development over 500m2 to achieve a rating of at least ‘Very Good Standard’ |
Policy 14,15, |
Policy 1, 2, 7, 17, 18, 19, 20, 21, 22, 23, 24, 26, 27, 28, 29, 32, 33, |
SA8 |
Developers, NBC, Commercial Users, WNDC / NBC, Building Control, WNDC, WNJPU |
>10% of qualifying developments fail to achieve the standard |
Review with Development Management Identify barriers preventing achievement |
Planning Permissions Granted Contrary to EA Advice on Water Quality or Flood Risk Grounds after failing the Sequential and / or exceptions test |
No applications should be granted contrary to EA Advice |
Policy 4, 5,25 |
Policy 9,19, 22, 26, 27, 28, 29,30 36 |
SA8, SA20, SA21, SA22 |
Environment Agency, NCC through Water Management Plan), NBC, Developers, WNDC/ Environment Agency Response-Objections to Applications, NBC, WNDC, WNJPU |
Permission granted contrary to advice |
Identify cause and consider justifi cation. Review implementation. Consider any remedial action Consider policy review |
NO2 Levels at existing designated AQMAs |
Improvements to air quality measurement areas
New development should address existing problems. Regular reporting of measurements |
N/A |
Policy 10,17, 20, 21, 22, 23, 24, 34 |
SA2 |
NBC, Environmental Services / NBC, DEFRA Reporting |
>5% increase in no of properties within designated AQMA;s, based on no of properties at 01/04/2011 |
Identify causes and identify what planning related solutions are available
Discuss with partners potential solutions |
Strategic Objective 8 - Sustainability |
|||||||
Objective: Ensuring the Central Area develops in a sustainable manner and helps create a positive framework for action on climate change |
|||||||
Policy Numbers: |
Policy 1, 2, 4, 5, 7, 9, 10, 14, 15, 16, 17, 18, 19, 20, 21, 22, 23, 24, 25, 26, 27, 28, 29, 30, 31, 32, 33, 34, 35, 36 |
||||||
Indicator |
Target |
Main Policy Delivered |
Additional Policies Delivered |
SA Objective Delivered? |
Main Agencies for delivery /Source for monitoring data |
Trigger |
Contingencies |
Sustainable Energy Generation within major new development through decentralised and renewable or low carbon sources |
To provide renewable energy at source through decentralised energy schemes considered on all new developments and regeneration schemes through open book analysis with NBC |
Policy 1 |
Policy 7, 17, 18, 19, 20, 21, 22, 23, 24, 26, 27, 28, 29, 30, 31, 32, 33, 34, 35, 36 |
SA8 |
Developers, WNDC, Environmental Services at NCC, NBC / WNDC, NCC, NBC Application Monitoring, WNJPU Monitoring |
>0 of major new development schemes (excluding those already permitted) that are proposed in the Joint Core Strategy and approved after 2014 that fail to provide decentralised energy opportunities |
Consider barriers to implementation and relevance of policy with Development Management and key organisations
Work with developers/ land owners to develop viable and suitable schemes
Review policy |
References within the table:
BID: Business Improvement District
DEFRA: Department for Environment Food and Rural Affairs EA: Environment Agency
NBC: Northampton Borough Council NCC: Northamptonshire County Council NEP: Northampton Enterprise Partnership
WNDC: West Northamptonshire Development Corporation WNJPU: West Northamptonshire Joint Planning Unit
Note:
‘Main Policy Delivered’ means policies that directly relate to delivery of the target.
‘Additional Policies Delivered’ means policies that contribute towards delivery of the target.
The start date / baseline for the purposes of targets is 1st April 2010.